Scope of Work:

  • Power plant piping installation (Sacramento, California)
  • Project Budget - $350 million

Challenges:

  • Dramatically improve production performance of ongoing piping installation
  • Recover piping installation schedule delays
  • Reduce piping installation completion costs

Results:

  • Reduced completion schedule from 28 months to 7 months
  • Reduced labor costs to complete piping work from $9.1 million to $2.5 million