Value - Performance - Sustainability  
Delivering better outcomes to capital programs      
 

Scope of Work:

  • Build new medical office building & clinic (Stockton, California)
  • Project Budget - $16 million

Challenges:

  • Project behind schedule from design and permit delays
  • Construction team working without an reliable plan - work performed in any available area

Results:

  • Saved 8 weeks on schedule
  • Synchronized production for floor completion using “cellular configurations” to increase throughput
  • Production team restricted from working in areas not fully available until design and permit issues are resolved
  • Effective planning systems implemented to determine work areas and sequence increasing positive cooperation between trades