Scope of Work:

  • Build new airport terminal (London, England)
  • Project Budget - £4.2 billion ($7.90 billion)

Challenges:

  • Coordinate activities of 80 concurrent projects
  • Manage work of 5,500 trade & support personnel
  • Single gate access with deliveries every 30 seconds
  • On-site inventory storage limited to one day supply
  • Operating under high security

Results:

  • First on-time delivery of major UK civil project in past 40 years
  • Saved in excess of £125 million on £1.25 billion in civil work
  • Improved productivity up to 40%
  • Achieved all milestones
  • Significant reduction in safety incidents
  • Reduced reinforcement fabrication lead times from 2 weeks to 2 days
  • Reduced pre-cast fabrication lead times from 12 weeks to 5 days
  • Reduced supply chain response times from weeks to days and from days to hours
  • Synchronized flow of deliveries
  • Increased on-site production of concrete without increasing the quantity of equipment